Fraser River Pile and Dredge was contracted by BC Ferries to perform life extension repairs and upgrades to Tsawwassen Berth 3. The catwalks to the South Breakwater required replacement as they had reached the end of their service life and the Berth 3 dolphins, ramps and aprons required repairs or upgrades to extend their life for an additional 10 years.
From November to December 2019, FRPD conducted marine and land repairs that included demolition of 60 timber piles, replacing timber fender panels, installing new catwalk sections, reinstalling apron sections and updating the lower ramp.