Metro Vancouver required immediate debris clearing at the Cariboo Dam to restore safe gate operation and protect downstream infrastructure. FRPD was mobilized on an urgent basis to remove accumulated material restricting water flow.


Problem

Debris buildup at the dam gates posed operational and safety risks. The work needed to be completed quickly within a confined and sensitive area, using equipment capable of precise removal without damaging gate structures.


Solution

FRPD deployed an 80-ton crane with a clamshell bucket to remove accumulated debris and restore full gate function. Crews worked efficiently under Metro Vancouver direction to re-establish safe flow conditions.


Key Facts
  • Mobilized 80T crane with clamshell bucket
  • Removed obstructing debris from Cariboo Dam gates
  • Restored clear flow paths and operational performance
  • Completed work under urgent response timelines